The purpose of Task 107 is to prepare a periodic progress report summarizing the pertinent system safety management and engineering activity that occurred during the reporting period.


TASK DESCRIPTION

The contractor shall prepare a periodic system safety progress report summarizing general progress made relative to the system safety program during the specified reporting period, and projected work for the next reporting period.  


DATA.

The contractor will prepare a report in contractor format that contains the following information:


A brief summary of activities, progress, and status of the safety effort in relation to the scheduled program milestones.  It shall highlight significant achievements and problems. It shall include progress toward completion of safety data prepared or in work.  


Newly recognized significant hazards and significant changes in the degree of control of the risk of known hazards.  


Individual hazard resolution status and status of all recommended corrective actions that have not been implemented.  


Significant cost and schedule changes that impact the safety program.  


Discussion of contractor documentation reviewed by the system safety function during the reporting period. Indicate whether the documents were acceptable for content and whether or not inputs to improve the safety posture were made. 


Proposed agenda items for the next system safety group/working group meeting, if such groups are formed


DETAILS TO BE SPECIFIED IN THE CONTRACT


Imposition of Tasks 101 and 107.


Specification of progress reporting period.